MIL-S-22824E
5.1.1.2 Disassemble. The screw pin shall be removed from one end of the
spreader bars and the upper leg assemblies. The upper legs shall be positioned
along the length of the spreader bars on one side, and the four lower legs
positioned along the opposite side. The screw pins shall be replaced in the
shackles.
5.1.1.3 Cleaning and drying. Prior to the application of preservative
compounds or paint, surfaces shall be cleaned by process C-1 and dried by any
applicable procedure of MIL-P-116.
5.1.1.4 Unprotected surfaces. Unprotected exterior metal surfaces requiring
the application of a contact preservative in accordance with MIL-P-116 and not
specifically provided for herein shall be preserved as follows:
5.1.1.5 Wire rope. Wire rope shall be preserved method I by coating with
type P-1 or P-19 preservative. The preservative shall be applied to all
surfaces of the wire rope. Excess preservative shall be removed by swabbing or
draining. The preservative shall be allowed to dry (at least 4 hours). The
wire rope shall be bundled or coiled and wrapped with a barrier material and
secured.
5.1.2 Commercial.
The equipment shall be preserved in accordance with
ASTM D 3951.
5.2 Packing.
Packing shall be level A, B, or commercial, as specified (see
6.2).
5.2.1 Level A. Each complete sling assembly shall be packed in a box
conforming to PPP-B-601, overseas type; or PPP-B-621, class 2. Contents shall
be cushioned, blocked, and braced to prevent movement within the container.
5.2.2 Level B. Each complete sling assembly shall be packed as specified
for level A except that the box shall be domestic type or class I.
5.2.3 Commercial.
The equipment shall be prepared for shipment in
accordance with ASTM D 3951.
5.3 Marking.
Marking shall be in accordance with MIL-STD-129.
6.
NOTES
(This section contains information of a general or explanatory nature that
may be helpful, but is not mandatory.)
6.1 Intended use. The sling assemblies covered by this specification are
intended for use in cargo handling operations for shipboard loading of vehicles.
6.2 Acquisition requirements.
Acquisition documents should specify the
following:
a.
Title, number, and date of this specification.
b.
Size of sling assembly required (see 1.2).
c.
Issue of DODISS to be cited in the solicitation, and if required, the
specific issue of individual documents referenced (see 2.1.1 and 2.2).
9
For Parts Inquires submit RFQ to Parts Hangar, Inc.
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business